First
fix electrical complete to the lounge area and all other rooms
including the hall and kitchen diner. Wall have been made good ready for
finishing and decoration works to begin.
The
external insulation was complete today, but unfortunately the window
reveals could not be complete as no insulation panels to suit were not
available on site. Lawtech confirmed to us that they would be on site
first thing tomorrow. This however caused us some concern; the rendering
finishing team had just arrived on site that morning to commence their
works but was unable to proceed due to other trades not finishing. We
did raise our concerns with Lawtech with regards to the impact on the
programme, but they assured us the time would be made up.
The SHB flow and return pipe work are sealed within the sleeves entering the kitchen. And below shows the kitchen first fix well on its way.

For
the first time we see the SHG panels operating as they should do by
showing signs of frost. It’s a pleasing moment as with them not
operating, this will not only delay the project but stop the tenant and
the family from moving back into their property.