The windows are commenced on the second day, which has been programmed in for 2 days from start to completion.This picture shows the existing steel frame apertures.
Due to a change in the Project Manager from Lawtech ano
ther
site meeting was arranged as there were changes to the agreed scaffold
staging and installation. The scaffold was duley altered 1st thing today with thanks to Kingsnorth Scaffolding.
Daniel
Ready our Project Manager was in discussion with the new Project
Manager of Lawtech and discussions again made about the agreed window
seal insulation and finished detail.
The
Vacuum Insulated Panels (VIPS) are being installed in their pre
machined panels. We laid them in a picture frame style then laid 15mm
Celotex, cut to the perimeters and door freeholds. This mainly ensures
that carpet gripper or nails do not penetrate the VIPs and make it fail.
The
VIPs were laid over a 1200 gauge polythene membrane which had been
stuck to the walls and laid onto the ground floor around the perimeters.
At
the end of today a call was put into our Consultants over the VIPs and
we were informed that the VIPS were to have a timber floor laid over.
This came as a surprise but not a big issue for our Company and we have
programmed it for tomorrow morning 1st thing.